How long it takes to frame a large house

How long does it take to frame a 10,000 square foot house?

The honest answer is that square footage barely predicts it. Four of our jobs, with real durations:

Job Size Crew Time
The Shire 12,000 sq ft, three stories 5 7 months to frame
McDaniels just under 11,000 sq ft 5 4 months, roughly two-thirds done
InterBel, Eureka just over 7,000 sq ft commercial — 8 days
The 12plex 19,000 sq ft — one of our first jobs at that scale

Seven thousand square feet in eight days, and twelve thousand in seven months. That is roughly fifteen times the daily rate, and the buildings are not fifteen times different in size.

A finished slab the length of the clearing with anchor bolts set around its edge and rainwater standing on it, equipment and a work trailer parked along the treeline beyond.
September 2025
The finished interior looking up into a dark timber truss beneath a pale boarded ceiling, a tall glazed wall opening onto grass and a small leaded window set high in the gable, with a mitre saw and stacked trim in the foreground.
April 2026
Shire Barn — Framing of a large barn-style custom home, over 6,000 square feet, with wall heights exceeding 22 feet.

What sets the schedule

Whether the material exists yet. This is the big one. Conventional framing runs on lumber that is already sitting in a yard. A custom timber house runs on timbers that are being cut for you, to spans nobody stocks, sometimes at a mill in another state. The frame does not start when the crew is ready. It starts when the timbers arrive.

Standing among the timber posts — heavy weathered uprights and diagonal braces carrying the floor above, sunlight falling in strips across the plywood between them.
The Shire — A 12,000 square foot, three-story residence carrying a timber package of close to two million dollars — one of the largest we've framed. The build includes reclaimed timber throughout, vaulted ceilings, a basement bowling alley, and a roughly 1,000 square foot elevated theater room.

How much of it repeats. InterBel was commercial — a shape that repeats, details that repeat, a crew that can get into a rhythm and stay there for a week. A custom house at The Shire’s level has almost nothing that repeats. Every bay is its own problem.

A crane reaching in over the slab with a sheathed panel swinging from its line, framed walls already standing in a row against the neighboring metal building.
InterBel — A commercial building just over 7,000 square feet, framed for H&C Construction from a complex, hardware-heavy set of prints.

How many parties have to agree. The hardest part of these jobs is not the cutting. It is making the whole thing happen — us, the timber framers, the general contractor, the lumber yards, the truss supplier — when everything is custom and every piece has a lead time attached. A beam that arrives in the wrong order doesn’t cost you a day, it costs you the sequence.

The weather you’re building through. Morton’s was a winter build and it cost us. That is its own subject.

How to read a schedule you’ve been given

If someone quotes you a framing duration on a custom timber house before the timber is ordered, they are quoting you the part they control and leaving out the part they don’t. Ask when the timbers are scheduled to arrive, and ask what the mill’s lead time is. That date, not crew size, is usually the one your schedule hangs on.

And ask what crew will actually be on it. Ours are five men on the big jobs, and they are the same five — we’ve never kept people on just because we needed bodies.

Quick answers

How long does a 10,000 square foot custom house take to frame?
On our jobs at that size, months rather than weeks. A 12,000 square foot timber frame house took a five-man crew seven months. An 11,000 square foot house was four months in and roughly two-thirds framed.
Why did a 7,000 square foot commercial building only take eight days?
Different building. InterBel in Eureka was conventional commercial framing — repetitive, stock material, no custom timber and nothing waiting on a mill. Square footage is not what sets the schedule.
What is the biggest cause of delay?
Waiting on custom material, and coordination between the parties — the timber framers, the general contractor, the lumber yards, the truss supplier. On a custom house nothing is off the shelf, so every piece has a lead time attached to it.

Got a set of plans?

We'll look at them and tell you what the framing side of it actually means — timber, schedule, and what we'd want to know before quoting it.